Long Pine Estates CIPP Rehabilitation Project

City of Riviera Beach Utility Special District

Project Update: Work Expected to Resume September 28, 2026

Due to the heavy rain events we have been experiencing, the contractor had to temporarily stop work on the project. Work is expected to resume Monday, September 28, 2026.

The project map below provides the anticipated work schedule for the Long Pine Estates area. Residents can use the color-coded phases to understand when work is expected to take place near their property.

Color-coded Long Pine Estates CIPP project map showing anticipated work phases through October 26, 2026

While this work is being performed, please limit activities that use large volumes of water, such as doing laundry, dishwashing, flushing toilets, and bathing. During the sewer lining process, your service connection will be temporarily closed off for a few hours. Every service lateral will be fully opened and back in service by the end of each workday.

If you detect a chemical odor during liner installation, you may be smelling styrene, a component of the resin used to saturate the sewer liner. The odor should dissipate once installation is complete.

Before work begins, pouring a gallon of water into sinks, floor drains, and other drainage openings—especially those that are seldom used—should help prevent odor from entering your home or building. If you detect an odor, open windows or turn on a fan to help ventilate the space.

Anticipated Project Schedule

  • September 14, 2026
  • September 28, 2026
  • October 5, 2026
  • October 12, 2026
  • October 19, 2026
  • October 26, 2026

Please note: These dates are anticipated phase start dates and may change due to weather, field conditions, or other unforeseen circumstances. Residents should use the map as a planning guide.

Lift Station 8 Force Main Replacement Project

City of Riviera Beach Utility Special District

Project map showing the Lift Station 8 force main replacement area along West 30th Street
Lift Station 8 force main replacement project area

The City of Riviera Beach Utility Special District will commence a pipe bursting project to replace the force main from Lift Station 8 to the discharge point. This project is structured to reduce the amount of lane or road closures, but residents will experience them during this project.

The majority of this project will occur on West 30th Street between Avenue O and President Barack Obama Highway.

Crews plan to begin this work on Monday, August 17, 2026, and the project should be completed prior to September 25, 2026.

Questions About the Project?

Please call the Utility District offices at (561) 845-4185.